US Army Corps of Engineers

Cougar Dam

Wednesday June 3, 2026

New Date:

HourTotal Outflow cfsGeneration Flow cfsSpill cfsForebay ElevationTailwater ElevationAverage Head
1 313 1577.50 1252.47 325.03
2 313 1577.50 1252.48 325.02
3 313 1577.51 1252.48 325.03
4 313 1577.54 1252.48 325.06
5 313 1577.51 1252.47 325.04
6 318 1577.53 1252.49 325.04
7 313 1577.52 1252.47 325.05
8 313 1577.54 1252.48 325.06
9 313 1577.56 1252.46 325.10
10 295 1577.55 1251.49 326.06
11 291 1577.55 1251.47 326.08
12 291 1577.57 1251.50 326.07
13 227 1577.56 1252.43 325.13
14 318 1577.58 1252.47 325.11
15 318 1577.57 1252.48 325.09
16 313 1577.57 1252.46 325.11
17 313 1577.57 1252.48 325.09
18 313 1577.59 1252.46 325.13
19 318 1577.60 1252.48 325.12
20 318 1577.59 1252.49 325.10
21 313 1577.59 1252.47 325.12
22 313 1577.59 1252.48 325.11
23 309 1577.60 1252.50 325.10
24 313 1577.61 1252.47 325.14
AVG 308   1577.56 1252.35 325.21
MAX 318   1577.61 1252.50 326.08
MIN 227   1577.50 1251.47 325.02