Draft 2025 Fish Passage Plan (FPP)
& Change Forms

* Change Forms FINALIZED after March 1, 2025, are NOT included in the print version of the 2025 FPP.
Draft Chapters Change Forms Date
Posted
Change Form
Status
Draft Chapter 1 - Overview
Draft Chapter 2 - Bonneville Dam 25BON001 - Unit 10 Fixed-blade Range 6-FEB-2025 FINALIZED
Draft Chapter 3 - The Dalles Dam 25TDA001 - Spill Patterns 6-FEB-2025 FINALIZED
Draft Chapter 4 - John Day Dam 25JDA001 - Clarify Unit Priority 6-FEB-2025 FINALIZED
25JDA002 - Clarify Emergency Bypass Terminology 6-FEB-2025 FINALIZED
25JDA003 - Clarify SMF Sampling 14-FEB-2025 FINALIZED
25JDA004 - Unit 2 Fixed-Blade Range 6-FEB-2025 FINALIZED
25JDA005 - Spillbay 2 Outages 6-FEB-2025 FINALIZED
25JDA006 - Daytime Spill Hours 6-FEB-2025 FINALIZED
Draft Chapter 5 - McNary Dam 25MCN001 - Reference to Surface Spill 6-FEB-2025 FINALIZED
Draft Chapter 6 - Ice Harbor Dam 25IHR001 - Reference to Surface Spill 6-FEB-2025 FINALIZED
25IHR002 - Bypass Start Date 6-FEB-2025 FINALIZED
25IHR003 - Bypass End Date 6-FEB-2025 FINALIZED
25IHR004 - STS Amp Reading 6-FEB-2025 FINALIZED
25IHR005 - Orifice Backflush 6-FEB-2025 FINALIZED
25IHR006 - Orifice Preference 6-FEB-2025 FINALIZED
25IHR007 - Remove Section 2.5.1 6-FEB-2025 FINALIZED
25IHR008 - Remove Section 2.3.2.7 6-FEB-2025 FINALIZED
Draft Chapter 7 - Lower Monumental Dam 25LMN001 - Reference to Surface Spill 6-FEB-2025 FINALIZED
25LMN002 - RSW Maintenance 6-FEB-2025 FINALIZED
25LMN003 - Channel Velocity 6-FEB-2025 FINALIZED
25LMN004 - Fishway Temperature Monitoring 6-FEB-2025 FINALIZED
25LMN005 - Dewatering Structure 6-FEB-2025 FINALIZED
Draft Chapter 8 - Little Goose Dam 25LGS001 - Reference to Surface Spill 6-FEB-2025 FINALIZED
25LGS002 - Fishway Cooling Pump Inspections 14-FEB-2025 FINALIZED
Draft Chapter 9 - Lower Granite Dam 25LWG001 - Reference to Surface Spill 6-FEB-2025 FINALIZED
25LWG002 - AWS Pumps RTS 6-FEB-2025 FINALIZED
Draft Appendices
Change Forms Date
Posted
Change Form
Status
Draft Appendix A - Special Ops & Studies 25AppA001 - Doble Test Schedule 12-FEB-2025 FINALIZED
Draft Appendix B - Transport Plan
Draft Appendix C - BPA Load Shaping Guidelines
Draft Appendix D - Ops for Non-Listed Species
Draft Appendix E - Fish Operations Plan (FOP) N/A (coordinated via RIOG) ------ ------
Draft Appendix F - Dewatering Fish Salvage
Draft Appendix G - Adult Trap Ops
Draft Appendix H - CHJ Turbine Dewatering
Draft Appendix I - DWR Turbine Maintenance
Draft Appendix J - Smolt Facility Protocols 25AppJ001 - LMN Sampling 6-FEB-2025 FINALIZED
25AppJ002 - JDA Sampling 6-FEB-2025 FINALIZED
25AppJ003 - IHR Sampling 6-FEB-2025 FINALIZED
Draft Appendix K - Acronyms
Draft Appendix L - Predator Mgmt Plans 25AppL001 - Predator Mgmt Updates 6-FEB-2025 FINALIZED
 