Draft Chapter 1 - Overview
Draft Chapter 2 - Bonneville Dam
25BON001 - Unit 10 Fixed-blade Range
6-FEB-2025
FINALIZED
Draft Chapter 3 - The Dalles Dam
25TDA001 - Spill Patterns
6-FEB-2025
FINALIZED
Draft Chapter 4 - John Day Dam
25JDA001 - Clarify Unit Priority
6-FEB-2025
FINALIZED
25JDA002 - Clarify Emergency Bypass Terminology
6-FEB-2025
FINALIZED
25JDA003 - Clarify SMF Sampling
14-FEB-2025
FINALIZED
25JDA004 - Unit 2 Fixed-Blade Range
6-FEB-2025
FINALIZED
25JDA005 - Spillbay 2 Outages
6-FEB-2025
FINALIZED
25JDA006 - Daytime Spill Hours
6-FEB-2025
FINALIZED
Draft Chapter 5 - McNary Dam
25MCN001 - Reference to Surface Spill
6-FEB-2025
FINALIZED
Draft Chapter 6 - Ice Harbor Dam
25IHR001 - Reference to Surface Spill
6-FEB-2025
FINALIZED
25IHR002 - Bypass Start Date
6-FEB-2025
FINALIZED
25IHR003 - Bypass End Date
6-FEB-2025
FINALIZED
25IHR004 - STS Amp Reading
6-FEB-2025
FINALIZED
25IHR005 - Orifice Backflush
6-FEB-2025
FINALIZED
25IHR006 - Orifice Preference
6-FEB-2025
FINALIZED
25IHR007 - Remove Section 2.5.1
6-FEB-2025
FINALIZED
25IHR008 - Remove Section 2.3.2.7
6-FEB-2025
FINALIZED
Draft Chapter 7 - Lower Monumental Dam
25LMN001 - Reference to Surface Spill
6-FEB-2025
FINALIZED
25LMN002 - RSW Maintenance
6-FEB-2025
FINALIZED
25LMN003 - Channel Velocity
6-FEB-2025
FINALIZED
25LMN004 - Fishway Temperature Monitoring
6-FEB-2025
FINALIZED
25LMN005 - Dewatering Structure
6-FEB-2025
FINALIZED
Draft Chapter 8 - Little Goose Dam
25LGS001 - Reference to Surface Spill
6-FEB-2025
FINALIZED
25LGS002 - Fishway Cooling Pump Inspections
14-FEB-2025
FINALIZED
Draft Chapter 9 - Lower Granite Dam
25LWG001 - Reference to Surface Spill
6-FEB-2025
FINALIZED
25LWG002 - AWS Pumps RTS
6-FEB-2025
FINALIZED
Draft Appendices
Change Forms
Date
Posted
Change Form
Status
Draft Appendix A - Special Ops & Studies
25AppA001 - Doble Test Schedule
12-FEB-2025
FINALIZED
Draft Appendix B - Transport Plan
Draft Appendix C - BPA Load Shaping Guidelines
Draft Appendix D - Ops for Non-Listed Species
Draft Appendix E - Fish Operations Plan (FOP)
N/A (coordinated via RIOG)
------
------
Draft Appendix F - Dewatering Fish Salvage
Draft Appendix G - Adult Trap Ops
Draft Appendix H - CHJ Turbine Dewatering
Draft Appendix I - DWR Turbine Maintenance
Draft Appendix J - Smolt Facility Protocols
25AppJ001 - LMN Sampling
6-FEB-2025
FINALIZED
25AppJ002 - JDA Sampling
6-FEB-2025
FINALIZED
25AppJ003 - IHR Sampling
6-FEB-2025
FINALIZED
Draft Appendix K - Acronyms
Draft Appendix L - Predator Mgmt Plans
25AppL001 - Predator Mgmt Updates
6-FEB-2025
FINALIZED